High-Level Conceptual Study of Substations for Early Development in a New Market

24. February 2022

Solution provider

Semco Maritime
More from Semco Maritime

Want to see this solution first hand?

Add the case to your visit request and let us know that you are interested in visiting Denmark

THE SOLUTION
Project development support involving identification of the most economic conceptual design for several offshore substations. Determination of transmission voltage, reactive compensation and key investor information for c. 2.5 GW of offshore wind generation in a new market.

Competences and systems:
Choice of optimal voltage and reactive compensation needs
Design and pricing of reactive power stations and c. 2,500 MW offshore substations

Estimated CAPEX
Transport feasibility scenarios
High-level investor information, including overview, system descriptions and indicative layouts